We are continuing the construction, and we remind you that the commissioning of the house is very soon - there are 6 months left, and the most interesting thing is ahead. In the meantime, the report for November.
In the house №1:
- installation of heating risers on stairwells up to the 25th floor has been completed;
- installation of light-enclosing constructions from 20 on 26 floors proceeds;
- performed work on the installation of floor screed up to the 20th floor;
- performed work on the arrangement of the roof
installation of a heating system up to the 26th floor was performed;
- works on the device of horizontal distribution of water supply to 26 floors are executed;
- performed work on the installation of plaster from the 4th to the 13th floor inclusive;
- finishing works have been started in common areas and technical premises.
In the house №2:
- completed work on the installation of reinforced concrete monolithic roof frame and parapets;
- installation of windows up to the 20th floor
- start work on the installation of light-enclosing structures from 20 to 26 floors
- performed work on the installation of cement-sand screed from the 4th to the 10th floor;
- works on installation of fire-fighting risers up to the 25th floor were performed;
- installation of heating risers is completed.