Construction progress in November
3D tour
Dial
All News

The course of construction in November

November 2021

We are continuing the construction, and we remind you that the commissioning of the house is very soon - there are 6 months left, and the most interesting thing is ahead. In the meantime, the report for November.


In the house №1:

- installation of heating risers on stairwells up to the 25th floor has been completed;

- installation of light-enclosing constructions from 20 on 26 floors proceeds;

- performed work on the installation of floor screed up to the 20th floor;

- performed work on the arrangement of the roof

installation of a heating system up to the 26th floor was performed;

- works on the device of horizontal distribution of water supply to 26 floors are executed;

 - performed work on the installation of plaster from the 4th to the 13th floor inclusive;

 -  finishing works have been started in common areas and technical premises.


In the house №2:

- completed work on the installation of reinforced concrete monolithic roof frame and parapets;

- installation of windows up to the 20th floor

- start work on the installation of light-enclosing structures from 20 to 26 floors

- performed work on the installation of cement-sand screed from the 4th to the 10th floor;

- works on installation of fire-fighting risers up to the 25th floor were performed;

- installation of heating risers is completed.