The course of construction in November

November 2021

We are continuing the construction, and we remind you that the commissioning of the house is very soon - there are 6 months left, and the most interesting thing is ahead. In the meantime, the report for November.


In the house №1:

- installation of heating risers on stairwells up to the 25th floor has been completed;

- installation of light-enclosing constructions from 20 on 26 floors proceeds;

- performed work on the installation of floor screed up to the 20th floor;

- performed work on the arrangement of the roof

installation of a heating system up to the 26th floor was performed;

- works on the device of horizontal distribution of water supply to 26 floors are executed;

 - performed work on the installation of plaster from the 4th to the 13th floor inclusive;

 -  finishing works have been started in common areas and technical premises.


In the house №2:

- completed work on the installation of reinforced concrete monolithic roof frame and parapets;

- installation of windows up to the 20th floor

- start work on the installation of light-enclosing structures from 20 to 26 floors

- performed work on the installation of cement-sand screed from the 4th to the 10th floor;

- works on installation of fire-fighting risers up to the 25th floor were performed;

- installation of heating risers is completed.