Construction progress October 2023

October 2023

Works that were carried out in October:


House 1

• Installation of metal framed floor slabs on cold transitions – 100%;

• Protection of elevator portals – 100%;

• Installation of metal framing of technological holes of the smoke removal system – 100%;

• SPDS: total readiness 40%;⠀


Facade works

SPOK - pressing and decorative bar - 160 m2 (general readiness 95%);

- NPF: Inner yard - frames (10%) 160 m2 (general performance of insulation 100%, frame 90% covered with tiles 15%);

- NPF: IQ center – 100%;

- NPF: SEU – made tiles (8%) 120 m2 (general execution frame 100%, tiles 15%);

- NPF: Main facade - SPOK 97%, NPF 80%.


House 2

• Installation of metal framed floor slabs on cold transitions – 100%;

• Protection of elevator portals - from the 4th to the 12th floor;

• Installation of metal framing of technological holes of the smoke removal system – 100%;

• SPDS: B2 – 2% done (total readiness 40%);


Facade works

SPOK - clamping and decorative bar - clamping and decorative bar 210 m2. (total readiness 99%.)

- NPF: Inner courtyard - 10% done (total readiness 45%);

- NPF: IQ center - 10% done (total readiness 90%);

- NPF: Main facade - 15% done (total readiness 60%)

- NPF: From the Dnipro side – 100%.


Stylobatus

• Installation of ceramic tile floor covering of technical premises - 1 piece of work was completed in the server room. and dispatchers – 2 pcs (mark 0.000);

• Construction of reinforced concrete monolithic stairs - СХ-1 at grades -0.100 - 3.500;

• The installation of metal racks in the entrance groups - the stylobate is 100% completed;

• SCS (Internet) – 3,300 – trays 100%, cable 100%;

• OS (security signaling) – 3,300 – cable 100%, without installation of the power supply cable of the extenders;

• LCD (access control) – 3,300 – cable 100%, without controller power supply;

• CCTV (video surveillance) – 3,300 – cable 100%, without installation of equipment;

• SPDS: done 2% (total readiness 55%);

• Ventilation completed - 1.5% (total availability 32%).


We continue to work.