Works that were carried out in October:
House 1
• Installation of metal framed floor slabs on cold transitions – 100%;
• Protection of elevator portals – 100%;
• Installation of metal framing of technological holes of the smoke removal system – 100%;
• SPDS: total readiness 40%;⠀
Facade works
SPOK - pressing and decorative bar - 160 m2 (general readiness 95%);
- NPF: Inner yard - frames (10%) 160 m2 (general performance of insulation 100%, frame 90% covered with tiles 15%);
- NPF: IQ center – 100%;
- NPF: SEU – made tiles (8%) 120 m2 (general execution frame 100%, tiles 15%);
- NPF: Main facade - SPOK 97%, NPF 80%.
House 2
• Installation of metal framed floor slabs on cold transitions – 100%;
• Protection of elevator portals - from the 4th to the 12th floor;
• Installation of metal framing of technological holes of the smoke removal system – 100%;
• SPDS: B2 – 2% done (total readiness 40%);
Facade works
SPOK - clamping and decorative bar - clamping and decorative bar 210 m2. (total readiness 99%.)
- NPF: Inner courtyard - 10% done (total readiness 45%);
- NPF: IQ center - 10% done (total readiness 90%);
- NPF: Main facade - 15% done (total readiness 60%)
- NPF: From the Dnipro side – 100%.
Stylobatus
• Installation of ceramic tile floor covering of technical premises - 1 piece of work was completed in the server room. and dispatchers – 2 pcs (mark 0.000);
• Construction of reinforced concrete monolithic stairs - СХ-1 at grades -0.100 - 3.500;
• The installation of metal racks in the entrance groups - the stylobate is 100% completed;
• SCS (Internet) – 3,300 – trays 100%, cable 100%;
• OS (security signaling) – 3,300 – cable 100%, without installation of the power supply cable of the extenders;
• LCD (access control) – 3,300 – cable 100%, without controller power supply;
• CCTV (video surveillance) – 3,300 – cable 100%, without installation of equipment;
• SPDS: done 2% (total readiness 55%);
• Ventilation completed - 1.5% (total availability 32%).
We continue to work.