Work is underway on the EDELDORF HILLS construction site! We share with you a digest for September.
In the house №1:
- installation of heating risers on stairwells up to the 25th floor is underway;
- installation of windows, window frames, glazing up to the 15th floor continues;
- floor screed up to the 14th floor is being laid;
- work on the installation of fans has begun;
- installation of a heating system up to the 20th floor was performed;
- horizontal water supply to the 17th floor is being carried out;
- equipment is installed in the boiler room;
- installation of chimneys is carried out.
In the house №2:
- concreting of stairwells and marches to the 26th floor was completed;
- brickwork of walls and partitions to the 26th floor is finished;
- concreting of the slab of the engine room is completed;
- installation of water supply and heat supply pipes up to the 26th floor;
- all roofing works are completed.
We invite you to see for yourself.