Construction work does not stop for a minute:
⠀
House 1
• Installation of the main heat pipe riser - from the 3rd to the 26th floor
• Heating and water supply - 100% completed by floor
• Sewerage Completed by 95%
• Electrical networks, completed on the 25th floor:
- installation of grounding wire in apartments
- lighting of apartment doors
- installation of sockets in the MZK
• Low current networks: risers, sleeves, trays 13-17 floors have been installed
• Plastering of the walls of the MZK up to the 17th floor
• Arrangement of SPOK 20-27 floors
• MOP door: installed up to the 19th floor
• Installation of the screed up to the 19th floor
• Installation of two 630 kg elevators and two 1000 kg elevators
House 2
• Roof: Performed hydraulic tests on the first half of the roof
• 100% of the horizontal distribution of water supply and heating
• Radiators are installed except for the riser where the lift is placed
• Arrangement of combs for water supply and heating
• Sewerage Completed up to the 25th floor
• Electrical networks, completed on the 15th floor:
- installation of grounding wire in apartments
- lighting of apartment doors
- installation of sockets in the MZK
• Low current networks: risers, sleeves, trays 13-17 floors are installed
• Plastering of the walls of the MZK up to the 16th floor
• Arrangement of SPOT 20-27 floors
• MOP doors: installed up to the 14th floor
• Installation of the screed up to the 25th floor
• Installation of two 630 kg elevators and two 1000 kg elevators
Stylobatus
• Masonry works for the redevelopment of the lobby
• Ringing of the water supply network has been completed
• Pump: Unbundling completed
• Reinforcement of structures for a light lantern
• Completed the insulation of the walls of the stalemate, except the lobby
• Installation of the smoke removal system on the 2nd floor of the parking lot - 70% completed
• Installation of two 630 kg elevators
Work has begun on the insulation of technical premises and parking spaces.