Work is underway at the EDELDORF HILLS construction site! We are sharing with you the June digest.


In the house number 1:

✔️ installation of ventilation units on the 25th floor;

✔️ polishing of the 26th floor;

✔️ brick laying of walls and partitions of the 23rd floor;

✔️ installation of metal lintels and pledges on the 26th floor;

✔️ installation of PVC pipes on the 11th floor;

✔️ installation of double-glazed windows, 4-20 floors.

In house number 2

✔ Reinforcement of landings and flights of the 25th floor;

✔️ brick laying of walls and partitions of 19-22 floors;

✔️ installation of heating and water supply in apartments on the 5th, 6th, 9th floors;

✔️ installation of trays on the 15th floor.

We invite you to see for yourself.