We continue construction, and report on new stages: the building has begun to be "dressed up" - installation of the facade.
House 1
- Low current networks: - laying of cables for SCS systems 4-24 floors;
- Electrical networks: - lighting of technical premises;
- Arrangement of SPOK: 80%;
- Arrangement of the NVF: 80%;
- Plastering of the walls of the MZK (corridors) - 23rd floor;
- Installation of two elevators of 630 kg and one of 1000 kg;
- The installation of the 1000 kg elevator has been completed, commissioning works;
- Installation of fire doors: - on internal stairs up to the 15th floor;
- Execution of internal gas supply works;
- Manufactured and delivered to the facility for installation of fire doors of elevator halls;
- The cleaning of the MZK - corridors on the residential floors has begun;
- Laying floor-wall tiles - 4, 5, 6 floors.
House 2
- Completion of wiring of heating networks, installation of radiators on the 26th floor;
- Electrical networks: - installation of MZK lighting networks on the 22nd floor;
- Arrangement of SPOK: 90%;
- Arrangement of the NVF: 90%;
- Plastering of the walls of the MZK, internal stairs;
- Installation of two 630 kg elevators and two 1000 kg elevators;
- Installation of fire doors: - on the internal stairs to the 14th floor;
- Performing work on the improvement of the operated roof;
- Manufactured and delivered to the facility for installation of fire doors in elevator halls.
Stylobatus
- Installation of technical underground ventilation systems;
- Installation of the air support system on the +4,400;
- Completion of works on the installation of a light lantern in the ceiling of the first floor;
- Performance of adjustment work in the pump room;
- Carrying out work on strengthening the stalemate;
- Execution of works on the insulation of the main heating line;
- Installation of fire doors in technical premises.
Work has begun on the insulation of technical premises and parking spaces.