Хід будівництва жовтень

September 2021

October at EDELDORF HILLS was extremely productive: a whole set of works was completed in both houses!

We share the digest:


In the house №1:

• installation of heating risers on stairwells up to the 25th floor has been completed;

• installation of windows, window frames, glazing up to the 18th floor continues;

• work continues on casting the floor screed to the 17th floor;

• work on installation of fans proceeds;

• installation of a heating system up to the 20th floor was performed;

• horizontal water supply distribution up to 24 floors is underway;

• installation of chimneys continues;

• finishing works have been started in public places.